The log home of Scott and Stephanie Bass was delivered October 5, 2004 to Dinwiddie, Virginia. They chose a modified Graystone with the interior garage becoming another bedroom, adding a porch and a deck to the back as well as a detached garage. The ever popular Genesis logs (with an extra course) with a dovetail corner make up the walls of this log home.
| July 13 |
 |
Land clearing and stump burning. |
| October 6 |
 |
The hurricanes managed to wash nearly a foot of dirt where it didn't need to be, but subfloor is complete and on to the first course of logs! |
| October 8 |
 |
Log courses go up, with window and door jambs in place. Master bedroom in distance. |
| October 9 |
 |
Last course up in places. This wall on the front porch has quite a few logs with darker grain. Dry weather has been a big help with construction. |
| October 11 |
 |
Back view, log walls nearly complete, garage in foreground. |
| October 12 |
 |
Front left view of finished log walls. Interior framing is the next step. |
| October 14 |
 |
8x12 Dougals Fir support beams are installed and interior framing is started. |
| October 15 |
 |
A bit of rainy weather from the front view of the house. Interior framing mostly finished, and garage walls started. |
| October 18 |
 |
Decks and porches are installed and house wrap for garage. |
| October 22 |
 |
All the conventional trusses are up, garage too. Great room in center has vaulted scissor trusses instead of flat conventional ones. |
| October 27 |
 |
View of front porch, more work on the roof, OSB added and felt paper started. |
| October 29 |
 |
Felt paper is on, now work on overhangs and beams for back porch roof. |
| November 2 |
 |
Back porch looks nice with heavy timbers, garage log siding is installed. |
| November 5 |
 |
Garage gables and overhangs look good. |
| November 9 |
 |
Work on gable ends, overhangs, and porch ceilings. |
| November 12 |
 |
Garage slab is poured, roof trim is going up. |
| November 16 |
 |
Interior of Kitchen from Great Room side, scissor trusses in center of house. Shingles delivered. |
| November 19 |
 |
Wow! Gables finished, shingles up and garage doors installed. |
| November 23 |
 |
Back porch & deck: electrical wired and windows going in. |
| November 30 |
 |
Front View, windows all installed. |
| December 3 |
 |
Great Room, decorative beams added. |
| December 10 |
 |
Exterior doors start to go up, exterior cedar trim as well. Plumbing is started.. |
| December 17 |
 |
Plumbing and electrical being installed. |
| January 11 |
 |
All exterior doors are installed, front porch railing finished too. |
| February 12 |
 |
Lots of work done inside, all plumbing and electrical done by owners. Genesis interior siding going up on interior walls of great room and hallways. |
| February 15 |
 |
Great Room: gas fireplace made from logs and timbers. Plenty of electrical sockets still being installed. |
| February 22 |
 |
A week vacation provides plenty of time to work on the house! Sheetrock ceilings are being installed. |
| February 25 |
 |
Sheetrock still going up on ceilings, insulation installed in great room scissor trusses (it will be blown in for flat trusses), work done on chimney. |
| March 1 |
 |
A view of the other side of the great room, all insulated. |
| March 9 |
 |
Another view of great room. Sheetrock going up in closets, light fixtures cut out. |
| March 25 |
 |
View of great room and fireplace with new gas logs. Sheetrock is up in great room and spackled. Kitchen cabinets delivered! |
| March 29 |
 |
Kitchen cabinets installed, Stephanie is sanding down interior log walls, still working on ceilings and walls. |
| April 5 |
 |
Game Room: antler lights installed with nice spackled ceiling, other lights installed too and kitchen countertops. |
| April 12 |
 |
Master Bath with tile, interior walls, lights, and cabinets! Interior walls and ceilings look about done, lots of lighting and cabinetery installed. Tile laid in bathrooms and utility room, plus gutters! |
| April 19 |
 |
Hallway out of the Master Bedroom, right wall has been sealed with Minwax polyurethane. |
| April 26 |
 |
Bathroom view, more polyurethaning done, plumbing and cabinets finished. |
| May 3 |
 |
Kitchen view, appliances all installed, some window trim as well and flooring has been started. |
| May 10 |
 |
Great Room, flooring in the whole house nearly complete! |
| May 24 |
 |
Front Porch, railings and steps going up. Flooring all finished. |
| May 31 |
 |
Back Deck, railings and stairs nearly done. |
| June 7 |
 |
Master Bath: mirrors in; tub finished out; trim on walls, doors, and windows complete; and bear accents added! |
| June 14 |
 |
Front Bedroom, trim on walls, doors, and windows nearly done. Outlets and door knobs being installed. |
| June 23 |
 |
Master Bedroom, finishing work nearly complete (railings on back deck can be seen). |
| June 30 |
 |
Great Room, beams finished and trimmed out. Temporary Occupancy Permit granted! |
| July 6 |
 |
Finished and decorated hearth, Occupancy Permit on July 8! Still work to do, of course! |